Probably mentioned elsewhere here, but I thought I'd bring it into one thread for visibility.
As of 12 June 2024 these are the UK sites listed in the Ionity Tracker (and from local planning) as in construction (most distant announcement to most recent)
Frimley
Entered 551 days ago
(Due to be energised around 19 June 2024)
Greenock
Entered 546 days ago
(entered on app)
York
Entered 541 days ago
(complete awaiting energisation)
Singing Kettle
Entered 352 days ago
Leicester
Entered 329 days ago
02/10/23 - updated planning application with 12 additional charge points (6 x Alpitronic HYC dual-head units) to the original 12 x ABB
(complete awaiting energisation)
Ayr
Entered 225 days ago
Doncaster
Entered 208 days ago
(groundworks almost complete, posts in place)
Sheffield
Entered 205 days ago
(entered on app)
Abergavenny
Entered 205 days ago
South Normanton
Entered 205 days ago
(complete awaiting energisation)
Dungannon (NI)
Entered 180 days ago
Dundee
Entered 174 days ago
Sunderland
Entered 85 days ago
Lancaster North
Entered 71 days ago
Edinburgh, Shawfair Business Park
Entered 55 days ago
09/04/24 - link. Due to open autumn 2024
Bristol - Village Hotel
Entered 6 days ago
Planning approved on 1 Feb 2024, P23/03488/F
Hull - Village Hotel
Entered yesterday
Planning approved on 18 April 2024, 23/03522/FULL
Cambridge, expansion - additional 18 charge points
Due by end of 2024
Peterborough, expansion - additional 18 charge points
Due by end of 2024
Beaconsfield, expansion - battery system planned
TBC. See link
Wrexham, Ramada Hotel
APPROVED, P/2023/0278
Droitwich Spa
30/04/23 in planning, W/23/00687/FUL
Almondsbury
22/02/24 WITHDRAWN, P23/02088/F
Cross Hands, Llanelli
20/03/24 WITHDRAWN, PL/06697
Haverfordwest
APPROVED, 23/0646/PA
Manchester, Eccles (M30 7EY)
25/01/24 in planning, PA/2023/0497
Southport
30/01/24 in planning, DC/2024/00197
Gloucester
28/03/24 in planning S.24/0598/FUL
Bristol (Eastgate)
APPROVED, 23/04014/F
Dartford, Doubletree Hilton
02/04/24 In planning 24/00365/FUL
I will provisionally add the 33 new Village Hotels / Ionity sites below (in alphabetic order) as announced on 12 September. As more details become available I can update / edit this post.
Aberdeen - APPROVED, 240077/DPP
Basingstoke - APPROVED, 24/00361/FUL
Birmingham Dudley - APPROVED, 23/1606
Birmingham Walsall - APPROVED, 23/1601
Blackpool - APPROVED, 24/0024
Bournemouth - APPROVED, 7-2024-9177-EH
Bracknell - 12/04/24 in planning 24/00193/FUL
Bristol - APPROVED, P23/03488/F
Cardiff - 24/01/24 in planning, 24/00164/FUL
Chester St David's - 19/03/24 in planning, FUL/000203/24
Coventry - APPROVED, PL/2024/0000321/FUL
Edinburgh - 16/05/24 WITHDRAWN, 24/00133/FUL
Farnborough
Glasgow - 24/01/24 in planning, 24/00164/FUL
Hull - PERMITTED, 23/03522/FULL
Leeds North - REFUSED, 23/07573/FU, REFUSED again, 24/01878/FU
Leeds South - REFUSED, 24/00376/FU. REFUSED again, 24/01877/FU
Liverpool - 15/03/24 in planning 24/00127/FUL
London Watford - PERMITTED, 24/0224/FUL
Maidstone - PERMITTED, 24/501357/FULL
Manchester Ashton
Manchester Bury - 26/02/24 in planning 23/01367/FUL
Manchester Cheadle - APPROVED DC/091638
Manchester Hyde - 19/12/23 in planning, 23/01106/FUL
Newcastle - 16/02/24 in planning 24/00200/FUL
Nottingham - 19/01/24 in planning, 24/00034/FUL
Portsmouth
Solihull - WITHDRAWN, PL/2023/02638/PPFL
Southampton Eastleigh
Swansea - APPROVED, 2023/2626/FUL
Swindon - 28/03/24 in planning, S/24/0368
Warrington - APPROVED, 2023/01545/FUL
Wirral - 16/02/24 in planning, APP/24/00220
[edits to OP in red]
As of last count there will be 85 Ionity sites in the UK total:
- Opened 29
- 17 in construction (include 2 VH sites)
- 8 in planning, and
- 31 Village Hotels sites in planning
The rough timetable, if it can be believed, for the Village Hotels sites (compared to the average Ionity construction time in the UK), is very aggressive indeed.
All these sites to be operational by 2024 apparently.
As of 12 June 2024 these are the UK sites listed in the Ionity Tracker (and from local planning) as in construction (most distant announcement to most recent)
Frimley
Entered 551 days ago
(Due to be energised around 19 June 2024)
Greenock
Entered 546 days ago
(entered on app)
York
Entered 541 days ago
(complete awaiting energisation)
Singing Kettle
Entered 352 days ago
Leicester
Entered 329 days ago
02/10/23 - updated planning application with 12 additional charge points (6 x Alpitronic HYC dual-head units) to the original 12 x ABB
(complete awaiting energisation)
Ayr
Entered 225 days ago
Doncaster
Entered 208 days ago
(groundworks almost complete, posts in place)
Sheffield
Entered 205 days ago
(entered on app)
Abergavenny
Entered 205 days ago
South Normanton
Entered 205 days ago
(complete awaiting energisation)
Dungannon (NI)
Entered 180 days ago
Dundee
Entered 174 days ago
Sunderland
Entered 85 days ago
Lancaster North
Entered 71 days ago
Edinburgh, Shawfair Business Park
Entered 55 days ago
09/04/24 - link. Due to open autumn 2024
Bristol - Village Hotel
Entered 6 days ago
Planning approved on 1 Feb 2024, P23/03488/F
Hull - Village Hotel
Entered yesterday
Planning approved on 18 April 2024, 23/03522/FULL
Cambridge, expansion - additional 18 charge points
Due by end of 2024
Peterborough, expansion - additional 18 charge points
Due by end of 2024
Beaconsfield, expansion - battery system planned
TBC. See link
Wrexham, Ramada Hotel
APPROVED, P/2023/0278
Droitwich Spa
30/04/23 in planning, W/23/00687/FUL
Almondsbury
Haverfordwest
APPROVED, 23/0646/PA
Manchester, Eccles (M30 7EY)
25/01/24 in planning, PA/2023/0497
Southport
30/01/24 in planning, DC/2024/00197
Gloucester
28/03/24 in planning S.24/0598/FUL
Bristol (Eastgate)
APPROVED, 23/04014/F
Dartford, Doubletree Hilton
02/04/24 In planning 24/00365/FUL
I will provisionally add the 33 new Village Hotels / Ionity sites below (in alphabetic order) as announced on 12 September. As more details become available I can update / edit this post.
Aberdeen - APPROVED, 240077/DPP
Basingstoke - APPROVED, 24/00361/FUL
Birmingham Dudley - APPROVED, 23/1606
Birmingham Walsall - APPROVED, 23/1601
Blackpool - APPROVED, 24/0024
Bournemouth - APPROVED, 7-2024-9177-EH
Bracknell - 12/04/24 in planning 24/00193/FUL
Bristol - APPROVED, P23/03488/F
Cardiff - 24/01/24 in planning, 24/00164/FUL
Chester St David's - 19/03/24 in planning, FUL/000203/24
Coventry - APPROVED, PL/2024/0000321/FUL
Edinburgh - 16/05/24 WITHDRAWN, 24/00133/FUL
Farnborough
Glasgow - 24/01/24 in planning, 24/00164/FUL
Hull - PERMITTED, 23/03522/FULL
Leeds North - REFUSED, 23/07573/FU, REFUSED again, 24/01878/FU
Leeds South - REFUSED, 24/00376/FU. REFUSED again, 24/01877/FU
Liverpool - 15/03/24 in planning 24/00127/FUL
London Watford - PERMITTED, 24/0224/FUL
Maidstone - PERMITTED, 24/501357/FULL
Manchester Ashton
Manchester Bury - 26/02/24 in planning 23/01367/FUL
Manchester Cheadle - APPROVED DC/091638
Manchester Hyde - 19/12/23 in planning, 23/01106/FUL
Newcastle - 16/02/24 in planning 24/00200/FUL
Nottingham - 19/01/24 in planning, 24/00034/FUL
Portsmouth
Solihull - WITHDRAWN, PL/2023/02638/PPFL
Southampton Eastleigh
Swansea - APPROVED, 2023/2626/FUL
Swindon - 28/03/24 in planning, S/24/0368
Warrington - APPROVED, 2023/01545/FUL
Wirral - 16/02/24 in planning, APP/24/00220
[edits to OP in red]
As of last count there will be 85 Ionity sites in the UK total:
- Opened 29
- 17 in construction (include 2 VH sites)
- 8 in planning, and
- 31 Village Hotels sites in planning
The rough timetable, if it can be believed, for the Village Hotels sites (compared to the average Ionity construction time in the UK), is very aggressive indeed.
All these sites to be operational by 2024 apparently.